Aramco MFC Contract: Installation of New Fuel Gas Particulate

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Western & Northwestern Region, KSA
End User Saudi Aramco
Client Saudi Aramco
Project Management
Consultant
Type of Project
Total Value (SAR) 2.3 Million Saudi Riyal
Start Date
Finish Date
Total Land Area
Total Built-up Area

Work Description

NWC-SWCC Connection Points Bulk Meter Projects

Scope of Work

  • Construction of Flow Meter and Valve Chambers (160 No’s)
  • Supply & Installation of Isolation Valves (160 No’s)
  • Supply & Installation of Flow Meters (160 No’s)
  • Supply & Installation of GRP Kiosk & Units(160 No’s)
  • Supply & Installation of Electrical Panels for each GRP Kiosk
  • Supply & Installation of Carbon Steel Pipe & Fittings
  • Supply & Installation of Instrumentation & SCADA
  • CS Pipe Wrapping
  • Water Quality Monitoring Station
  • Internal & External FBE Coating on C.Steel Pipes & Fittings
  • Online Anlyzer/Water Quality Monitoring Station
  • Total Alkalinity Measurement/Water Quality Monitoring Station

Supply & Installation of Underground Chilled Water Network Piping at Saudi Cargo Terminal – KAIA DC Project, Jeddah

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location King Abdulaziz Int’l Airport (KAIA), Jeddah
End User SAL – Saudi Logistic Services
Client Saudi Tabreed District Cooling Company
Project Management AECOM
Consultant SNC-Lavalin
Type of Project Pipeline
Total Value (SAR) 12.5 Million Saudi Riyal
Start Date Dec, 2022
Finish Date May, 2023
Total Pipeline Length 3,500 LM
Total Built-up Area

Work Description

NWC-SWCC Connection Points Bulk Meter Projects

Scope of Work

  • Construction of Valve Chambers (12 No’s)
  • Supply & Installation of Isolation Valves (8 No’s)
  • Supply & Installation of Dismantling Joints (6 No’s)
  • Supply & Installation of Automatic Air Vents(4 No’s)
  • Supply & Installation of Washout Valves (6 No’s)
  • Supply & Installation of 24X14inch Hot-Tapping Connection
  • Supply & Installation of Pre-Insulated Carbon Steel Pipes (3,415 m)
  • Supply & Installation of Leak Detection System
  • Flushing, Passivation and Cleaning of the System

Design and Build of RO Expansion in Sudair Industrial and Business City – Modon Project

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Sudair, Riyadh, KSA
End User
Client
Project Management
Consultant
Type of Project
Total Value (SAR) 17.38 Million Saudi Riyal
Start Date Dec, 2022
Finish Date Dec, 2023
Total Land Area
Total Built-up Area

Work Description

Site Work, Civil, Architecture, Structural, Mechanical, Electrical and Landscape Works.

Scope of Work

A – Site Construction

  • Construction of Building for Faculty of Dentistry,
  • Construction Concrete and wall works,
  • Construction finishing works, Hollow metal doors,windows and  frames,
  • Landscape works.

B – Electro-Mechanical Works

  • Air Handing Unit (AHU), Exhaust Fans (EF), HVAC works, Fire Fighting works ,
  • Power outlet works , Transformer , Ring Main Unit (RMU), Motor Control Center (MCC)
  • MDB, Data and Telephone System, IP CCTV System,
  • Low Voltage & Medium Voltage Cables works and BMS System,
  • Conveying system elevators (4 pcs), Freight Elevator (1 pcs)
  • Total Area of Building and Landscaping: Faculty land on around 7100 m2 with 15.000 m2 construction area.

Burns Treatment Center (First Phase) in the New University Hospital

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client Imam Abdulrahman Bin Faisal University
Project Management University PM
Consultant University PM
Type of Project Hospital Building
Total Value (SAR) 15.1 Million Saudi Riyal
Start Date Apr, 2021
Finish Date Jul, 2023
Total Land Area 15,000 m2
Total Built-up Area 7,100 m2

Work Description

Site Work, Civil, Architecture, Structural, Mechanical, Electrical and Landscape Works.

Scope of Work

A – Site Construction

  • Construction of Building for Faculty of Dentistry,
  • Construction Concrete and wall works,
  • Construction finishing works, Hollow metal doors,windows and  frames,
  • Landscape works.

B – Electro-Mechanical Works

  • Air Handing Unit (AHU), Exhaust Fans (EF), HVAC works, Fire Fighting works ,
  • Power outlet works , Transformer , Ring Main Unit (RMU), Motor Control Center (MCC)
  • MDB, Data and Telephone System, IP CCTV System,
  • Low Voltage & Medium Voltage Cables works and BMS System,
  • Conveying system elevators (4 pcs), Freight Elevator (1 pcs)
  • Total Area of Building and Landscaping: Faculty land on around 7100 m2 with 15.000 m2 construction area.

NWC-SWCC Connection Points Bulk Meter Projects

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Western & Northwestern Region, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 119.5 Million Saudi Riyal
Start Date Aug, 2021
Finish Date Jan, 2023
Total Land Area
Total Built-up Area

Work Description

NWC-SWCC Connection Points Bulk Meter Projects

Scope of Work

  • Construction of Flow Meter and Valve Chambers (160 No’s)
  • Supply & Installation of Isolation Valves (160 No’s)
  • Supply & Installation of Flow Meters (160 No’s)
  • Supply & Installation of GRP Kiosk & Units(160 No’s)
  • Supply & Installation of Electrical Panels for each GRP Kiosk
  • Supply & Installation of Carbon Steel Pipe & Fittings
  • Supply & Installation of Instrumentation & SCADA
  • CS Pipe Wrapping
  • Water Quality Monitoring Station
  • Internal & External FBE Coating on C.Steel Pipes & Fittings
  • Online Anlyzer/Water Quality Monitoring Station
  • Total Alkalinity Measurement/Water Quality Monitoring Station

Medical Complex for Female Students – Medical Faculties in the University City (Dentistry Medicine Faculty)

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client Imam Abdulrahman Bin Faisal University
Project Management University PM
Consultant
Type of Project Hospital Building
Total Value (SAR) 61.68 Million Saudi Riyal
Start Date May, 2019
Finish Date May, 2022
Total Land Area 15,000 m2
Total Built-up Area 7,100 m2

Work Description

Site Work, Civil, Architecture, Structural, Mechanical, Electrical and Landscape Works.

Scope of Work

A – Site Construction

  • Construction of Building for Faculty of Dentistry,
  • Construction Concrete and wall works,
  • Construction finishing works, Hollow metal doors,windows and  frames,
  • Landscape works.

B – Electro-Mechanical Works

  • Air Handing Unit (AHU), Exhaust Fans (EF), HVAC works, Fire Fighting works ,
  • Power outlet works , Transformer , Ring Main Unit (RMU), Motor Control Center (MCC)
  • MDB, Data and Telephone System, IP CCTV System,
  • Low Voltage & Medium Voltage Cables works and BMS System,
  • Conveying system elevators (4 pcs), Freight Elevator (1 pcs)
  • Total Area of Building and Landscaping: Faculty land on around 7100 m2 with 15.000 m2 construction area.

Construction and Equipping of Environmental Safety and Control Department Building (ESCD)

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Yanbu, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management Parsons
Consultant Parsons
Type of Project Building
Total Value (SAR) 49.32 Million Saudi Riyal
Start Date Dec, 2018
Finish Date Dec, 2020
Total Land Area
Total Built-up Area

Work Description

Electrical & Mechanical works

Scope of Work

Site Civil and Mechanical Works:

  • Site preparation, construction of roads, potable and fire water distribution system, irrigation system and landscaping works.

Site Electrical Power Distribution System and Telecommunication:

  • Supply, delivery, erection, test and commission of package substation, medium voltage cabling, grounding system and construction of telecom duct banks, handholes as per contract drawing.

Environmental Safety & Control Department Building:

  • Construction of ESCD Building consist of implementation of civil, structure and architecture work, mechanical works and electrical works.
  • Construction of Pump Room beside the ESCD Building consisting of civil works, mechanical works and electrical works.

P&C Of District Cooling Plant in Community Area

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jubail, KSA
End User Royal Commission for Jubail and Yanbu
Client Royal Commission for Jubail and Yanbu
Project Management
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 159.73 Million Saudi Riyal
Start Date Jan, 2018
Finish Date Aug, 2020
Total Land Area
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

Site Infrastructure Works

  • Storm Water Piping System: 800 m.
  • Potable and Fire Water Piping System: 700 m.
  • Sanitary Water Piping System: 500 m.
  • Break Water Storage Steel Tank: 1 no. 6 m dia. Capacity 150 m³.
  • Potable Water Storage Steel Tank: 1 no. 9 m dia. Capacity 400 m³.
  • Make-Up Water Storage Steel Tanks: 2 nos. 14 m dia. Capacity 2,275 m³.
  • Thermal Energy Storage Steel Tank: 1 no. 23 m dia. Capacity 24,000 ton/hr.

Chiller Plant

  • Electric Operated Overhead Cranes: 2 nos. Lifting Capacity 15 ton.
  • Series Counter Flow Water Cooled Centrifugal Chillers: 6 nos. Capacity 3,000 TR each (TOTAL 18,000 TR).
  • Induced Draft Field Erected Counter Flow Cooling Towers: 3 nos. Capacity 12,400 GPM.
  • Chilled Water Pumps: 3 nos. TDH 3 bar, Capacity 9,000 GPM.
  • Condenser Water Pumps: 3 nos. TDH 4 bar, Capacity 9,000 GPM.
  • MV Switchgears: 2 nos. 4.16 kV and 3 nos. 13.8 kV
  • Diesel Generator: 1 no. 300 kVA

Pump Stations

  • Make-Up Water Pumps: 4 nos. TDH 2 bar, Capacity 376 GPM
  • Fire Pumps: 2 nos. TDH 9 bar, Capacity 750 GPM
  • Submersible Pumps: 2 nos. TDH 3.5 bar, Capacity 1,200 GPM
  • Excavation and Backfilling
  • Expansion Tanks
  • Basket Strainers
  • Firefighting FM200 Clean Agent System
  • Air Handling Units, Package Units, Fan Coil Units and Exhaust Fans
  • Chemical Treatment System
  • Access Control System & SCADA
  • Area Lightning System
  • Telecommunication System

Infrastructure & Electro-Mechanical Works for Wadi Al Hada Residential Compound

Project Description

MEP Contractor SASEL & FEMCO CONSORTIUM
Location Riyadh, KSA
End User Wadi Hanifah Real Est. Development
Client Wadi Hanifah Real Est. Development
Project Management Leman PM
Consultant SaudConsult
Type of Project Residential Compound
Total Value (SAR) 236 Million Saudi Riyal
Start Date May, 2019
Finish Date Feb, 2020
Total Land Area 250,000 m2
Total Built-up Area 150,000 m2

Work Description

Electrical & Mechanical works

Scope of Work

  • Residential compound of 549 units to be built on total land of around: 215,000 m2 with total build up area of around 150,000 m2 works as bellow:
  • Infrastructure work, Electrical and Mechanical works for Residential compound 549 units consisting of: 8no’s Villas 5 bedrooms duplex, 66no’s of 3 bed rooms duplex townhouse, 57no’s of 4 bedrooms triplex townhouse and 338 apartments distributed on 43 buildings. all these to be built on total land of around 215,000 m2 with total build up area of around 150,000 m2.
  • Work includes supply and install the following:
  • 4no’s of chillers 426kw/each
  • Pipes for chilled water, potable water, and firefighting network with required valves
  • Pipes and manholes for sewage system
  • Medium voltage cables network, low voltage cables network
  • 13no’s Oil Type Transformers
  • 5no’s RMU
  • Generators
  • MCC Panels
  • Fuel Tanks
  • BMS

Infrastructure for KFU Teaching Hospital Project in Al-Ahsa, Phase-2

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Al Ahsa, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management KFU-PM
Consultant Al-Saif Consultants
Type of Project District Cooling & Infrastructure
Total Value (SAR) 245.21 Million Saudi Riyal
Start Date Mar, 2015
Finish Date June, 2021
Total Land Area 1,000,000 m2
Total Built-up Area

Work Description

Civil, Electrical & Mechanical works

Scope of Work

Site Infrastructure

  • Excavation: 250,000 m³
  • Backfilling: 450,000 m³
  • Concrete Works: 10,000 m³
  • Precast Fence Wall: 3,000 m
  • Asphalt: 150,000 m²
  • Chilled Water Piping System: 1,000 m
  • Steam and Condensate Water Piping System: 2,000 m
  • Sewerage Piping System: 4,500 m
  • Potable Water Piping System: 5,000 m
  • Raw Water Piping System: 5,000 m
  • Fire Water Piping System: 4,000 m
  • Storm Water Piping System: 2,000 m
  • Irrigation Water Piping System: 6,000 m
  • Deep Well: 4 nos. 250 m
  • Deep Well Water Piping System: 1,000 m
  • Manholes: 110 nos. FRP
  • Water Steel Storage Tanks: 6 nos. Capacities 3,000 m³ each
  • LV, MV and Communication Ductbank: 13,000 m
  • Cabling: 33,000 m
  • Transformers and Substations: 26 nos up to 2,000 kVA
  • External Area Lightning: 950 nos.
  • Reverse Osmosis (RO) Plant: 750 m³/day

Generator Plant

  • Diesel Generators: 11 nos. 2,500 kVA
  • Underground Diesel Tanks: 3 nos. Capacity 40,000 Gallon

Chiller Plant 

  • Water Cooled Centrifugal Chiller: 2 nos. Capacity 2,151 TR each (TOTAL 4,302 TR)
  • Air Cooler Radiators: 16 nos. 269 TR
  • Lift Stations: 13 Nos., capacity of 8-12 m depth
  • Steam Calorifiers: 10 nos., 1600-5400 L
  • Heat Exchanges: 11 nos., 1675 kW & 1805 kW
  • Condensate Recovery Unit: 2 nos., 200 L each