Project Description

Main Contractor

Yuksel Insaat Saudia Co. Ltd.

Sub-Contractor

Faisal Electro-Mechanical Co. Ltd.

Location

Jubail, KSA

End User

Saline Water Conversation Corp. (SWCC)

Client

Saline Water Conversation Corp. (SWCC)

Project Management

SWCC-PM

Consultant

Type of Project

Water & Power

Total Value (SAR)

12.3 Million Saudi Riyal

Start Date

Sep, 1995

Finish Date

Nov, 1998

Total Duration

Total Land Area

Total Built-up Area

Work Description

Civil, Structural, Mechanical, & Electrical Works

Scope of Work

  • Fabrication, Painting, & Erection of about 835 MT of Steel Structure.
  • Erection of 669 sq. mt. of Steel Cladding
  • Fabrication & Installation of Assorted Piping: viz. 6,000 MT of RTR Pipes 4″ to 84″ dia., 5,000 MT. of S S Pipes 1″ to 16” dia., 2,000 MT of Pvc & uPVC Pipes 2″ to 8” dia. and 7,500 MT. of Cu. / GI Pipes 1″ to 8″ dia. and Pipe Racks.
  • Sandblasting, Painting and Installation of CS Pipes, and Insulation & Al.
  • Jacketing of Pipes.
  • Erection, Testing & Commissioning of Equipment: viz. High Pressure Pumps coupled with Motors & Recovery Turbines, Vertical Multi-stage Pressure pumps, Back-wash & Feed Pumps, Air Blowers, Compressors, Chemical Dozing Pumps, Static Mixers, Chemical Process Units, Exhaust Fans, Motor Operated Valves, and Over-head Cranes.
  • Laying, Termination & Testing of MV / LV Cables & Cable Racks for Building, Street / Security Lighting, Instrumentation & Control System, Data & Communication System.
  • Earthing & Bonding System for entire Plant.