Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Jeddah, KSA
End User Ministry of Higher Education
Client King Abdulaziz University
Project Management University PM
Consultant Fluor Consultants
Type of Project District Cooling & Infrastructure
Total Value (SAR) 43.87 Million Saudi Riyal
Start Date May, 2013
Finish Date Jan, 2014
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Supply and installation Chilled water pipilines. Pre-insulated pipes. 750, 600, 450, 400, 350, 300 mm diameter pipes total 7950 meter.
  • Supply and installation Packaged ETS Plant; Stainless Steel Double Plate Heat Exchanger, Structural Steel Base, Insulated Double Wall Plant Enclosure, Pumps, Motors and controllers including VFD Drive, Air Separator and Make-Up Water System, Expansion Tank, Chemical Treatment Systems and Chemical Pot Feeder, Valves, Gauges and Piping Accessories, Pipe and Pipe Supports, Pump Vibration Isolation. Electrical Equipments within Packaged ETS plant. DDC Control System with remote workstation Interface Panel. (7 nos. ETS Module. a- 1897Tons (6671.75Kw), b- 2520Tons (8862.84Kw), c- 3010Tons (10586.2Kw), d- 1964Tons (6907.4Kw), e- 2464Tons (8665.89Kw), f- 840Tons (2954.3Kw), g- 1768Tons (6218.1Kw), flanged ends.)