Project Description
| MEP Contractor | Faisal Electro-Mechanical Co. Ltd. |
| Location | Dhahran, KSA |
| End User | Ministry of Higher Education |
| Client | King Fahd University of Petroleum and Minerals |
| Project Management | University PM |
| Consultant | |
| Type of Project | District Cooling & Infrastructure |
| Total Value (SAR) | 9.05 Million Saudi Riyal |
| Start Date | May, 2013 |
| Finish Date | Nov, 2014 |
| Total Land Area | |
| Total Built-up Area |
Work Description
Mechanical Replacement Works
Scope of Work
- Supply, Installation and Testing & Commissioning of 4 nos. Water Cooled Centrifugal Chillers 550 TR capacity each (TOTAL 2,200 TR)
- Supply, Installation and Testing & Commissioning of 1 no. Water Cooled Centrifugal Chiller 750 TR capacity.
- Supply, Installation and Testing & Commissioning of 2 nos. Fire Absorption Liquid Chillers 200 TR capacity each (TOTAL 400 TR).
- Supply, Installation and Testing & Commissioning of 2 nos. Fire Absorption Liquid Chillers 250 TR capacity each (TOTAL 500 TR).