Taprogge Filters for Main Sea Water Header & Sea Water Desal Header with Disposal System

Project Description

Contractor FEMCO & Termomeccanica Consortium
Location Jubail, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 15.2 Million Saudi Riyal
Start Date Apr, 2007
Finish Date Feb, 2008
Total Land Area
Total Built-up Area

Work Description

Electrical, Mechanical, & Civil Works for Taprogge Filters

Scope of Work

  • Installation of 2 nos. dia. 120” and 6 nos. dia. 60” Debris Filter and Debris Container.
  • Supply & Installation of RTR Pipes with Fittings (dias. 120″, 108” & 60″) for Topragge Filter and Drain System.
  • Elect. System: Supply & Installation, of all necessary Cables, Accessories, & Termination for Start-up.
  • Supply & Erection of Main Chamber for 2 nos. 120″ Debris Filter & Drain Pit, and Line Civil Works.

High Point Terminal Ball Valve Replacement (Contracts No: 3400/0306)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Client Saline Water Conversion Corporation (SWCC)
Location Riyadh, KSA
Total Value (SAR) 815,000 SAR
Start Date Feb, 2006
Finish Date Mar, 2006

Work Description

Industrial Maintenance

Shuqaiq Desalination and Power Plant Boiler Piping Works (Contracts No: 11/1/1/3330)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Client Saline Water Conversion Corporation (SWCC)
Location Shuqaiq, KSA
Total Value (SAR) 565,340 SAR
Start Date Jan, 2006
Finish Date Feb, 2006

Work Description

Industrial Maintenance

Shuqaiq Desalination and Power Plant Boiler Maintenance (Contracts No: M11/454/15)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Client Saline Water Conversion Corporation (SWCC)
Location Shuqaiq, KSA
Total Value (SAR) 319,680 SAR
Start Date Dec, 2005
Finish Date Jan, 2006

Work Description

Industrial Maintenance

Provision of Isolating Facility – RQWTS Valve Chamber (HPT)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Location Riyadh, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 2.2 Million Saudi Riyal
Start Date Sep, 2005
Finish Date May, 2006
Total Land Area
Total Built-up Area

Work Description

Electrical, Mechanical & Civil Works for 80″ Butterfly Valve

Scope of Work

  • Excavation and Removal of two nos. of Standard PCCP Pipes – dia. 2000 mm x 15 meters long.
  • Installation of Temporary By-Pass Line – dia. 800 mm with 2 x 90 deg. Elbows.
  • Construction of Valve Chamber (3000 W x 5300 L x 7920 mm H )
  • Supply & Installation of dia. 2000 mm Isolating Butterfly Valve, with Flange Adaptors and Hardware.
  • Supply & Installation of dia. 2000 mm PCCP Pipe with Fittings
  • Installation of Thrust Blocks for Bulk Heads & subsequent Removal together with Temporary By-Pass Line.

Sewage Works Package 5, East side / City Fanar Project

Project Description

MEP Contractor FEMCO & YUKSEL Consortium
Location Dammam, KSA
End User
Client Rikaz Development Company
Project Management
Consultant
Type of Project District Cooling & Infrastructure
Total Value (SAR) 11.2 Million Saudi Riyal
Start Date Mar, 2005
Finish Date Aug, 2005
Total Land Area
Total Built-up Area

Work Description

Sewage System consisting of Sewage Network & Lifting Stations

Scope of Work

  • Supply & Installation of uPVC Pipes, diameter ranging from 150 to 400 mm.
  • FRP Pipes from 200 to 800 mm dia. including Valves, Fittings, Inspection Chambers and Manholes.
  • Excavation, De-Watering, Leveling, Back-filling, Compacting and Side Slope Protection.
  • Construction of Lifting Station and Booster Lifting Station which includes
  • Submersible Pumps, Motors, together with Discharge Pipes & Fittings, Check Valve, Gate Valve and Exhaust Ducts.
  • Construction of: Fence, Gates, Walkways, Asphalting,
  • Guard House, Generator Room, and Electrical Room.
  • Architectural Works include Concrete Masonry Units,
  • Elastomeric Membrane Roofing System,
  • Steel Doors & frames, Aluminum Windows,
  • Plastering, Painting, Tiling (interior & exterior) and Toilet Fittings.

Preparation of Infrastructure for the University City in Dammam Phase 4 & 6, Utility Works. (King Faisal University Permanent Campus in Dammam)

Project Description

MEP Contractor Faisal Electro-Mechanical Co. Ltd.
Location Dammam, KSA
End User Ministry of Higher Education
Client King Faisal University
Project Management University PM
Consultant Saud Consult
Type of Project District Cooling & Infrastructure
Total Value (SAR) 101.39 Million Saudi Riyal
Start Date Mar, 2005
Finish Date Nov, 2007
Total Land Area
Total Built-up Area

Work Description

Civil, Mechanical, & Electrical Infrastructure Works

Scope of Work

  • Excavation & Back-filling of 1,362,694 cu. mtr. of Soil,
  • Construction of 107,700 LM of Flexible Pavements
  • 92,200 LM of Curbs & Gutters and 61,000 sq. mtrs. of Sidewalks.
  • 769 LM of Underground Piping (FRP) were laid, and Water Tank of 1,800 cu.mtr. was constructed.
  • R.O Plant of 600 cu.mtr. / day capacity was installed with Water Well and 14.13 KM of Water Network Piping.
  • Sewage Treatment Plant (STP) and Sewage Lift Station is provided with
  • Installation of 5.12 KM of Sanitary Sewage Piping.
  • 5.34 KM of Irrigation Piping has been laid.
  • 50 mtrs. of LPG Pipes (above ground) have been installed with 2 nos. of LPG Tanks of 40,000 USG capacity.
  • 2 nos. of Centrifugal Chillers and 2 nos. of Cooling Towers have also been erected.
  • Electrical Works include: Installation of Power & Distribution Transformers,
  • LV Switchgear, and Street Lighting Poles
  • Communication & Data Processing Equipment, Telephone & Inter-com System.
  • Building Automation & Controls and Security Surveillance System were also added.

Refurbishment Works of Jeddah Phase 4 – Desalination Plant

Project Description

Main Contractor ACWA Power SASAKURA (APS)
Sub-Contractor Faisal Electro-Mechanical Co. Ltd.
Location Jeddah, KSA
End User Saline Water Conversation Corp. (SWCC)
Client Saline Water Conversation Corp. (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 40.5 Million Saudi Riyal
Start Date Sep, 2004
Finish Date Apr, 2007
Total Land Area
Total Built-up Area

Work Description

Rehabilitation Works of Evaporator Tube Bundles and modification of Vacuum System

Scope of Work

  • Removal and Replacement of Brine Pipes, Sea Water Pipes, Water boxes, Demisters & Manhole Covers.
  • Tube Bundles Demolishing & Replacement.
  • Removal and Replacement of: Vent Pipes, Tube Sheets Necks, Tube Support Plates and Intermediate Tube Sheets.
  • Insertion & Expanding of 53,200 nos. of 90/10 Cu.Ni. Tubes (O.D 19 mm x 25000 mm length.) with subsequent
    Leakage Test using Pressure Air.
  • Cleaning, Rust Removal, Sandblasting, & Coating Works.
  • Lining Works ( mounting SS lining material on evaporated internal surface above Demister for Corrosion Protection
    after cleaning )
  • Modification of Evaporator Venting & Vacuum System, Brine Gate Cover and inspection of Brine Heater Tubes.
  • Replacement of Pump Suction & Discharge Valves and Leakage Test.
  • All related Elect. & Instrumentation Works.

Jubail Desalination and Power Plant BS#3 (Contracts No: 14/2/1/2615)

Project Description

Contractor Faisal Electro-Mechanical Co. Ltd.
Client Saline Water Conversion Corporation (SWCC)
Location Jubail, KSA
Total Value (SAR) 737,429 SAR
Start Date Sep, 2003
Finish Date Feb, 2004

Work Description

Industrial Maintenance

Tank Farm Piping for MSF & RO Plants

Project Description

Contractor FEMCO & YUKSEL Consortium
Location Jubail, KSA
End User Saline Water Conversion Corporation (SWCC)
Client Saline Water Conversion Corporation (SWCC)
Project Management SWCC-PM
Consultant
Type of Project Water & Power
Total Value (SAR) 3.5 Million Saudi Riyal
Start Date Jul, 2003
Finish Date Jul, 2004
Total Land Area
Total Built-up Area

Work Description

  • Dismantling & Removal of dia. 32” Temporary Link Line, and dia 36” Temporary Suction Line,
  • 36” Temporary By-Pass Line, together with Butterfly Valves and Drain & Vent Valves.
  • Supply and Installation of Piping in the Pump House of Blending Station – BS 1.
  • Supply, Laying & Embedding of new Link Line ( for MSF 1 ) of dia. 32″, 36“, & Branch – off Line dia. 48” together with Valves.
  • Supply & Installation of Power Supply & Control Equipment for new monitoring equipment of Phase 1 Line of dia. 36
    (Flow meters, Hardness Analyzer, pH analyzer)
  • Supply & Installation of 3 nos. Valve Chambers, Cable Duct banks, and Manholes for Elect. System.
  • Civil Works for Yard Shaft & Cable Pulling Shafts.